Issue | We seem to have lost our budget numbers in the account schedules. Prior to this week, we could go into the account schedule and select the annual budget - this column is no longer populating. |
Solution | When new budget entries are imported from Excel, the analysis views must be updated as well. Go to Financial Management > Periodic Activities > Update Analysis views. For the Code filter choose or type ALL, then click OK. You will then see the message: All selected Analysis Views were updated successfully. This will update the Analysis view Budget entries |
Account Schedule Budget Print
Modified on: Mon, Dec 12, 2016 at 2:50 PM
Did you find it helpful? Yes No
Send feedbackSorry we couldn't be helpful. Help us improve this article with your feedback.